Steel, plumbing & backfilling… December 15th, 2018

This week, at the construction site, wood framers will be putting up the wall panels on the fourth floor and the excavator will be back-filling along between the north wall of the building and Bridge Street. Once the backfilling is complete, we expect to see the concrete barriers that hold the chain link fence pulled back closer to the building. In the meantime, mechanical, electrical and plumbing contractors will continue work on the building’s infrastructure and it’ll be super interesting this week to watch the steel contractor finish the steel details on the canopy and install the balconies for the apartments on the upper floors.